Scheduling And Progress Monitoring Analysis Construction Essay

Effective project management is important to be able to ensure that tasks are delivered within budget, time and also to the decided quality. It demands a comprehensive understanding of the key phases, that are critical to success, in the life cycle of an construction task. In aid of attaining good planning takes time, but it means that the job will be on budget, on time and also dangers are minimised. It makes sure organisational prices and client requirements are clear and known. Good planning has consequently to reduce waste products deliver better design. Furthermore, it can help the task team to manage better with hazards as they happen, which in any other case probably will cause greater wait and increased costs (Office of Administration Commerce, 2003).

This section explains the scheduling and improvement monitoring activities for managing the project with supporting processes like as change control. The program is also called enough time plan. 'The project sponsor, through the project manager, is in charge of scheduling and monitoring progress. A programme, in the context of construction tasks, is a timetable that identifies the work to be carried out as a series of activities and plots the time periods required to do and complete each activity and the interdependencies between each activity' (Office of Federal Commerce, 2003). 'Agenda is a diagrammatic representation of activities and their time romance. Also, schedule is known as project program. ' (Construction Industry Council, 1996).

A program also controls resources needed and their availability. It is essential to know possible risks or problems. The job director must check the timetable and improvement monitoring against progress already achieved in aid of understanding where issues and hazards are possibly to arise and to set up different course of action in order to reduce their impact. (Office of Federal government Commerce, 2003). 'Risk management is a center process within any business or group no matter size, activity or sector. Individuals and organizations can lose substantive amounts of money therefore of not paying sufficient focus on the recognition and management of dangers to their goals and also to the jobs they commission. In the same way, full advantage cannot be taken of possibly beneficial opportunities arising in the course of their activities if they are not regarded in good time'.

The project sponsor must can be used to identify those jobs that rest on the critical path. Critical route is the shortest possible time based on hypothesis about the responsibilities to be completed and the resources available. Time for the processes should be included as specific activities in the timetable of the project. 'The schedule is an estimate that is dependant on considered assumptions on issues such as likely risk' (Office of Administration Business, 2003). Some estimation might prove to be incorrect. Some deviations might be likely but these will accepted if indeed they do not have an effect on the critical course and the task is finished promptly. Techniques include pub and Gantt graphs and network planning improve progress monitoring. Club and Gantt graphs define an uncomplicated view of activities aligned with timetables. Network planning is particularly useful for sophisticated projects because it links reliant activities in a logical order (Office of Federal government Commerce, 2003).

The job sponsor must make an effort to ensure that final plan to be simple and straightforward. The networks of activities of the ultimate schedules, and the interrelationships between them should be advanced and comprehensive. They need to be rapidly known of the task sponsor that's the reason color-coded bar charts are used as management control documents (Office of Administration Commerce, 2003).

Schedule planning tasks

The project director must survey on schedule planning to the project sponsor with respect to the project team. The project manager must produce a work breakdown structure (WBS). WBS 'defines the task content of the task in conditions of basic elements, work deals, generic jobs and detailed duties' (Office of Government Commerce, 2003). The main plan planning must show how elements affect one another. It defines activities and also establishes the logical relationships of the actions. It determines the work content, the period and the required resources of each activity. Furthermore, it also identifies the critical course, which establishes the length of the task. Finally, it can maximize the time plan by reference leveling. 'Source leveling compares the determined requirements with those actually available and recalculates the network to pass on resources more equally' (Office of Federal Business, 2003).

Progress monitoring

'Progress monitoring includes looking at monthly progress studies made by the project administrator with others in the integrated project team' (Office of Authorities Commerce, 2003). Progress monitoring must concentrate on critical activities and alert the SPO's attention in the correct amount of time in order to appropriate activities to be studied at the earliest opportunity. The project sponsor must understand the full total rate of the complete progress to be able to judge the forecast conclusion date. In order to measure the progress, the percentage conclusion of an activity can be measure in terms of cost and time. The organized progress must be compared with the actual improvement. Also improvement can be measure the work happening by taking account of milestones of the task. Any impact on critical must be checked out in order to finish the project promptly. Furthermore progress can be monitored by the payment progress and from resources still required. (Office of Administration Commerce, 2003).

An essential factor of process monitoring is the process of tome control. A time control system can cover time budget, time plan and time checking. Time budget symbolizes the overall job duration as produced by specific constrains of the project in the deal strategy. It is the period which set onetime and from that minute becomes one of the most important guidelines for management of the project. Time plan is a department of total time into interlinked time allowances for identifiable activities, which may be defined start and carry out details. Time checking is monitoring enough time actually allocated to each activity and compared it with the allowance in enough time plan. If any divergence is revealed, it must be reported as soon as possible. (Office of Federal government Commerce, 2003).

In the situation that an activity on the critical route exceeds its time allowance later activities must re-sequenced, or make an effort to shorten the designed time for future critical activities by increasing the resources (extra cost) for the precise activities. If neither is possible to be achieved, the project will finish later part of the. The task sponsor must understand that time control is as essential during the planning phases as the building periods of the task. (Office of Government Business, 2003).

Progress reports

Progress reports are essential reports in the complete procedure for the project, because they keep the project sponsor prepared about the job progress. They discover problems and options for their resolution. On top of that, they provide the necessary information to permit the project sponsor to make decisions on time. Progress reports illustrate that the designed task team executes their responsibilities properly and that the management functions procedures and adjustments are operating efficiently. They provide an specialist, and a communication tool in a simple and complete format, for your task team. Furthermore they offer a time research for meetings and plans. In addition the gathering of reports by the office permits external monitoring and identify best practice and support of improvement in performance. (Office of Administration Commerce, 2003).

Change control

Change can be treated most efficiently through project planning and control. Change for just about any reason must be cured as a task risk. 'Changes to design, especially after agreement award, are one of the major causes of the time and cost overruns and poor value for money. Changes happen mainly therefore of unclear or ambiguous job explanation, poor communication, inadequate time put in in project planning and risk management, or changing circumstances' (Office of Federal Business, 2003).

Changes can be reduced by ensuring the project simple is comprehensive and has the stakeholders' agreement. They could be minimized by firmly taking profile of present and proposed legislation. Furthermore, early on discussions with stakeholders must be achieved in the early stages to be able to predict their requirements. Site investigations and conditions studies must be undertaken early in the levels. The designs must adequately develop early on in the job and definably before constructions plans are committed. Finally, a proactive job management in order to recognize and managing risks will have as a result to reduce changes (Office of Government Commerce, 2003).

A change control treatment must consider the factors, that will talk about below, before approval is given for the change. It must taking accounts of the reasons for the change, and because of its source, which is accountable for wanting the change. The consequences of the change in conditions of quality, cost and time. It must consider the potential risks and their effects from the change. Furthermore, alternatives to the proposed change must be assessed properly. It must checked out proposals for staying away from time overrun and source of financing of any cost overrun. Finally, it must consider consumer acceptance for the change. After an in depth analysis of the change confirms that it provides value of money and that the client allows any influences the authorization of the change is distributed by SRO. Furthermore, the investment decision manufacturer will approve any extra funding which exceeds the amount allowed in the chance allowance.

Also We Can Offer!

Other services that we offer

If you don’t see the necessary subject, paper type, or topic in our list of available services and examples, don’t worry! We have a number of other academic disciplines to suit the needs of anyone who visits this website looking for help.

How to ...

We made your life easier with putting together a big number of articles and guidelines on how to plan and write different types of assignments (Essay, Research Paper, Dissertation etc)