CE 2. 1

In this profession episode report, I'd like to spell it out my experience in Continuous Emission Monitoring System designing. CEMS systems are used for calculating flue gas for oxygen, carbon monoxide and carbon dioxide to calculate the combustion control in industrial monitoring purpose. Nowadays it is recognized as a standard to talk with various emission requirements. Factories are operating CEMS system consistently to obtain the emission files and send these data to respective express/federal regulators.

BACKGROUND

CE 2. 2

Chemtrols is one of the leading solutions providers in Process Gas Analytics, Environment Protection and Emission Monitoring, Flow Measurementation, Chemical research and Automation, Instrumentation alternatives, Data Handling and Flames & safeness Systems. It really is a technology innovated company controlled by several specialists having high technical skills and proven job management track data. You can find skilled teams to managing small to large projects; they will offer numerous levels of the job such as design, procurement, integration, checking, troubleshooting, commissioning and maintenance. They efficiently implemented many assignments in various sectors like Steel, Oil & Gas, Cement, Ability, Chemicals etc. as a specialized solution service provider.

CE 2. 3

On 2010, I had been designated as the Senior Project Engineer of continuous emission monitoring job for Saint Gobin Glass Ltd. It was a prestigious minute for me working with Chemtrols since the tasks were the to begin its kind in Chennai - India to gauge the SO2 emission from the using of flare stacks. The primary purpose of the proposed job included to making of analyzer system, planning of material specification, assembly with the analyser, calibration, assessment, timely delivery and site supervision of complete analyzer bundle. I was designated to reviewing the client specification and inquiries to supply the feedback if the facility could handle the job.

I conducted multiple specialized discussions with the customer to getting authorization on documents, launching changes/improvement to finalize the design prior to starting the fabrication. Because of various specific requirements from the client during engineering stage, I put re-examined a lot of factors to accomplish consumer requirements. Each and whenever I have submitted a written report to my supervisor about the cost, quality, functionality and schedule which were affected in the design.

CE 2. 4

I experienced performed the next activities to effectively complete the proposed job,

  1. I examine the project need/purchase order and clarified the complex queries that have been pending during sales stage. Also identified the range of work and materials to provide.
  2. I was authorized to generate the standards of materials necessary for the machine and procure the same by making use of procurement team.
  3. I was assigning careers to other associates those who involved in this project such as draftsman, development supervisors, fabricators, fitters, helpers, and electricians. I was responsible for arranging the drafting team for getting ready the anatomist drawings.
  4. I ready the weekly task status and regular progress report to the business as well as the customer for evaluation. These information help me to examine the project progress, budget and time schedule.
  5. I was conducted regular ending up in other team members to investigate the improvement of individual's process and effectively package all issues and troubles to obtaining the targets.
  6. I was frequently communicated with the client to confirm the design, quality, and progress of the jobs.
  7. I lead the team having executive, fabrication, production and tests for the Analyser systems.
  8. I was began to compare similar equipment from different manufacturers based on project requirement. It can help me to gauge the differences between price, quality, and consistency than it.
  9. I was rectified errors and errors made during executive/fabrication and execute an inquiry among my team to comprehend causes. After conclusion of every milestone, I perform a group conversation procedure with my team members for an examination about the same and guide them to achieve the next goal.

CE 2. 5

I have given the organizational composition of the proposed project in Fig 1

Fig 1: Organisation Com